Waterloo Region Connected
ION - Waterloo Region's Light Rail Transit - Printable Version

+- Waterloo Region Connected (https://www.waterlooregionconnected.com)
+-- Forum: Waterloo Region Works (https://www.waterlooregionconnected.com/forumdisplay.php?fid=14)
+--- Forum: Transportation and Infrastructure (https://www.waterlooregionconnected.com/forumdisplay.php?fid=25)
+--- Thread: ION - Waterloo Region's Light Rail Transit (/showthread.php?tid=14)

Pages: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353 354 355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 407 408 409 410 411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450 451 452 453 454 455 456 457 458 459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484 485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 501 502 503 504 505 506 507 508 509 510 511 512 513 514 515 516 517 518 519 520 521 522 523 524 525 526 527 528 529 530 531 532 533 534 535 536 537 538 539 540 541 542 543 544 545 546 547 548 549 550 551 552 553 554 555 556 557 558 559 560 561 562 563 564 565 566 567 568 569 570 571 572 573 574 575 576 577 578 579 580 581 582 583 584 585 586 587 588 589 590 591 592 593 594 595 596 597 598 599 600 601 602 603 604 605 606 607 608 609 610 611 612 613 614 615 616 617 618 619 620 621 622 623 624 625 626 627 628 629 630 631 632 633 634 635 636 637 638 639 640 641 642 643 644 645 646 647 648 649 650 651 652 653 654 655 656 657 658 659 660 661 662 663 664 665 666 667 668 669 670 671 672 673 674 675 676 677 678 679 680 681 682 683 684 685 686 687 688 689 690 691 692 693 694 695 696 697 698 699 700 701 702 703 704 705 706 707 708 709 710 711 712 713 714 715 716 717 718 719 720 721 722 723 724 725 726 727 728 729 730 731 732 733 734 735 736 737 738 739 740 741 742 743 744 745 746 747 748 749 750 751 752 753 754 755 756 757 758 759 760 761 762 763 764 765 766 767 768 769 770 771 772 773 774 775 776 777 778 779 780 781 782 783 784 785 786 787 788 789 790 791 792 793 794 795 796 797 798 799 800 801 802 803 804 805 806 807 808 809 810 811 812 813 814 815 816 817 818 819 820 821 822 823 824 825 826 827 828 829 830 831 832 833 834 835 836 837 838 839 840 841 842 843 844 845 846 847 848 849 850 851 852 853 854 855 856 857 858 859 860 861 862 863 864 865 866 867 868 869 870 871 872 873 874 875 876 877 878 879 880 881 882 883 884 885 886 887 888 889 890 891 892 893 894 895 896 897 898 899 900 901 902 903 904 905 906 907 908 909 910 911 912 913 914 915 916 917 918 919 920 921 922 923 924 925 926 927 928 929 930 931 932 933 934 935 936 937 938 939 940 941 942 943 944 945 946 947 948 949 950 951 952 953 954 955 956 957 958 959 960 961 962 963 964 965 966 967 968 969 970 971 972 973 974 975 976 977 978 979 980 981 982 983 984 985 986 987 988 989 990 991 992 993 994 995 996 997 998 999 1000 1001 1002 1003 1004 1005 1006 1007 1008 1009 1010 1011 1012 1013 1014 1015 1016 1017 1018 1019 1020 1021 1022 1023 1024 1025 1026 1027 1028 1029 1030 1031 1032 1033 1034 1035 1036 1037 1038 1039 1040 1041 1042 1043 1044 1045 1046 1047 1048 1049 1050 1051 1052 1053 1054 1055 1056 1057 1058 1059 1060 1061 1062 1063 1064 1065 1066 1067 1068 1069 1070 1071 1072 1073 1074 1075 1076 1077 1078 1079 1080 1081 1082 1083 1084 1085 1086 1087 1088 1089 1090 1091 1092 1093 1094 1095 1096 1097 1098 1099 1100 1101 1102 1103 1104 1105 1106 1107 1108 1109 1110 1111 1112 1113 1114 1115 1116 1117 1118 1119 1120 1121 1122 1123 1124 1125 1126 1127 1128 1129 1130 1131 1132 1133 1134 1135 1136 1137 1138 1139 1140 1141 1142 1143 1144 1145 1146 1147 1148 1149 1150 1151 1152 1153 1154 1155 1156 1157 1158 1159 1160 1161 1162 1163 1164 1165 1166


RE: ION - Waterloo Region's Light Rail Transit - GtwoK - 05-24-2016

Water / Duke was paved today, would hazard to guess that it'll open tomorrow.


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-24-2016

If you cancel the current order and go with another vendor, ion will not open until 2020.

These are not "sitting on the shelf" items. You get in a queue, and your equipment gets built.

The trains we are getting are a NA variant derived from the FLEXITY 2 platform in Europe and are "standard". Our trains are not custom in any way other than they're painted blue.

Look up vehicle delivery news articles and you'll see that even if we'd gone with CAF Or Siemens, we'd still likely have late trains.

This is not really a big deal.


RE: ION - Waterloo Region's Light Rail Transit - tomh009 - 05-24-2016

(05-24-2016, 07:00 PM)ijmorlan Wrote: We should just cancel the Bombardier order and get bog-standard LRVs from Siemens or Skoda or anybody who is willing to bid on the basis that they will actually deliver when promised. Is it really impossible to get vehicles in less than two years?

Take a look at when you could get delivery on an Airbus A320 NEO or a Boeing 737 MAX -- it's probably 2020 or later.  Trains are the same: they are built to order, and there is always a backlog, at least for any decent product.  And we don't just need one, either.

On top of that, there would be cancellation penalties, as I doubt this level of delays would give us cancellation rights.

EDIT: To operate in two years, we need to receive the first trains in less than one year.  It's just not going to happen with anyone else at this point.


RE: ION - Waterloo Region's Light Rail Transit - Pheidippides - 05-25-2016

I'd have to agree with others that unfortunately this is likely not the last delay in the vehicle production. The only hope I am holding out is that Bombardier has finally learned to under-promise and over-deliver instead of the other way around.

Perhaps Canard or someone can explain why if this is a "standard" product what makes it so challenging to produce on a regular schedule. Does Bombardier have the same production timeliness problems producing the European version of the Flexity at their European plants?


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-25-2016

It's a NEW standard, for North America, based on the FLEXITY 2 designed in Europe. The frames were being built at a Bombardier-acquired plant in Mexico and this was the first job for them (the FLEXITY Outlook trams for Toronto). They screwed them up and now production of the frames is being shifted to BBD's La Pocatiere facility in Quebec, which is winding down the TR Subway vehicle order for the TTC.

Thunder Bay COULD have cranked these out on schedule, like they do every other product they make, if it weren't for the shoddy frames. That put them so far behind that now they need to shift production of our train variant, the FLEXITY Freedom, to another plant - Millhaven (Kingston). Millhaven is just finishing up an order for Kuala Lumpur so they have capacity there now, too. That's also where the test track is, which the first Freedom LRV will use, so this all makes sense.

The problem is we're now riding a rolling wave of lateness which will eventually tighten up. But it will take a little bit of time (6 months).

We just have to sit tight and wait. Knee-jerk reactions of "cancel the order! Buy different trains!" Solve absolutely nothing and would only result in a far, far worse delay.


RE: ION - Waterloo Region's Light Rail Transit - BuildingScout - 05-25-2016

(05-25-2016, 07:51 AM)BrianT Wrote:
(05-25-2016, 07:16 AM)Pheidippides Wrote: I'd have to agree with others that unfortunately this is likely not the last delay in the vehicle production. The only hope I am holding out is that Bombardier has finally learned to under-promise and over-deliver instead of the other way around.

Perhaps Canard or someone can explain why if this is a "standard" product what makes it so challenging to produce on a regular schedule. Does Bombardier have the same production timeliness problems producing the European version of the Flexity at their European plants?

The problem seems to be the Mexican plant. Attention to detail is not the Mexican worker's strong point. When a good percentage of the work coming from Mexico has to be fixed, it slows the assembly of the cars.


There's something deeper at play here than what Bombardier admits to. First, given modern CAD/CAM design and manufacturing blue prints, it is not possible to just drill holes in the wrong place. Second, even if this somehow happened (e.g. uploaded the wrong set of blueprints) it doesn't take 8 months and a sliding schedule to fix. Third, car manufacturing plants in Mexico routinely win awards for quality, how come not Bombardier's? They owned that plant since 1992. Fourth, how come is the schedule even later after bringing La Pocatiere and Millhaven online?

A reporter should dig into this and find the true reasons of this debacle.


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-25-2016

It's a very high-level view of how manufacturing works to just blindly say "Modern production doesn't allow for mistakes". Trust me, it does. Coordinating multiple teams from multiple plants causes colossal errors.

Even Airbus isn't immune. Germany and France were using different service packs of their solid modelling software which used different K-factors for cable routing. Guess what happened when they put the first A380 together?

As I have said multiple times (I'm tired.), the changes are being made soon, and it takes time to bring these other facilities online with this project. These changes were just recently decided and they can't just INSTANTLY start totally reworking their production schedules, get jigs ready, order material etc... It is a 6 month rolling wave.


RE: ION - Waterloo Region's Light Rail Transit - tomh009 - 05-25-2016

(05-25-2016, 07:16 AM)Pheidippides Wrote: Perhaps Canard or someone can explain why if this is a "standard" product what makes it so challenging to produce on a regular schedule. Does Bombardier have the same production timeliness problems producing the European version of the Flexity at their European plants?

I thought the problems were not so much with the Metrolinx order of Flexity Freedom, which is indeed pretty much a standard product, but with the TTC order of Flexity Outlook, which is quite heavily customized to fit Toronto's needs.  And the Metrolinx order is in the queue behind the TTC order, so TTC delays hit us as well.

Or have I misunderstood this?


RE: ION - Waterloo Region's Light Rail Transit - tomh009 - 05-25-2016

More details and comments in this morning's Record, in a quite calm and balanced article:
http://www.therecord.com/news-story/6677484-lrt-rollout-delayed-bombardier-blamed/

And a positive, supportive editorial:
http://www.therecord.com/opinion-story/6688559-the-record-s-view-light-rail-is-still-worth-the-wait/


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-25-2016

They're ~80% similar. The frames and so on are all virtually the same. The nose cone is different on ours, ours are wider, doors on both sides, a different width truck is on ours... But all the same issues with Outlook trickle down to Freedom.


RE: ION - Waterloo Region's Light Rail Transit - timc - 05-25-2016

(05-25-2016, 09:05 AM)tomh009 Wrote: More details and comments in this morning's Record, in a quite calm and balanced article:
http://www.therecord.com/news-story/6677484-lrt-rollout-delayed-bombardier-blamed/

I didn't realize this was the case:

Quote:A new order from some other company would mean modifications to the actual light rail system, particularly the stations, because it is being built specific to the low floor trains from Bombardier.



RE: ION - Waterloo Region's Light Rail Transit - tomh009 - 05-25-2016

(05-25-2016, 09:05 AM)Canard Wrote: They're ~80% similar. The frames and so on are all virtually the same. The nose cone is different on ours, ours are wider, doors on both sides, a different width truck is on ours... But all the same issues with Outlook trickle down to Freedom.

But the TTC trams have at least a unique gauge and the ability to make tighter turns than the standard Flexity -- both of which would potentially impact the frames, would they not?

And the delays to date have been with the TTC version, because the Metrolinx order hasn't hit the production line yet -- or has it?


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-25-2016

(05-24-2016, 02:30 PM)dunkalunk Wrote:
(05-24-2016, 01:48 PM)Canard Wrote: There is a $1500/day/vehicle penalty to Bombardier.

Source? Smile

Quote:In the contract, the provision for late trains is $1,500 per day, per train, up to a maximum of $3.3 million. The region can also seek further damages.

Source: http://www.therecord.com/news-story/6677484-lrt-rollout-delayed-bombardier-blamed


RE: ION - Waterloo Region's Light Rail Transit - tomh009 - 05-25-2016

(05-25-2016, 09:17 AM)Canard Wrote:
(05-24-2016, 02:30 PM)dunkalunk Wrote: Source? Smile

Quote:In the contract, the provision for late trains is $1,500 per day, per train, up to a maximum of $3.3 million. The region can also seek further damages.

Source: http://www.therecord.com/news-story/6677484-lrt-rollout-delayed-bombardier-blamed

What's not clear is the date (or dates) when that penalty kicks in.


RE: ION - Waterloo Region's Light Rail Transit - Canard - 05-25-2016

The frames from a design standpoint on Outlook and Freedom "under the hood" are almost identical. Toronto's vehicles are narrower (so the roof and floor panels are narrower). The tighter curve radius means the distance between vehicles and swivel plate mounts are stretched a bit differently. The bogies/trucks are wider because TTC's gauge is a few inches wider than standard.

These are all very minor differences.

The same problems affecting Outlook affect Freedom.