08-17-2015, 12:49 PM
I've made some additions to the map to increase clarity.
Record article today about lots of impending work:
Tracks starting to arrive for LRT in Kitchener
Record article today about lots of impending work:
Tracks starting to arrive for LRT in Kitchener
The Record Wrote:...
Work continues along Charles, between Victoria and Borden, with local-only traffic access.
• Charles-Cedar intersection is expected to reopen by the end of the week, as are the Charles-Gaukel and Charles-Ontario intersections.
• Charles-Water will close for a month, as soon as Charles-Ontario reopens.
• Charles-Eby is expected to shut this week. It's not expected to reopen until mid-September.
Other work continues along the on-street sections of the light rail system:
• Northfield Drive, at the Conestoga Parkway, Waterloo — upgrading bridge to carry LRT tracks; lanes closed on Northfield and ramps to parkway shut through 2016.
• University Avenue at the CN track crossing is scheduled to reopen this week.
• Seagram Drive (at CN railway crossing) — closed three weeks as LRT tracks installed.
• Caroline Street, between Willis Way and William Street, Waterloo — closed through the summer, and William to Allen also shut.
• King Street, between Allen and Union streets, Waterloo — closed; Allen-King intersection shut through Sept 21.
• King at Mount Hope Street in Kitchener — closes for two days this week.
• King at Green Street — closed Tuesday through Friday.
• King, between Moore Avenue and Victoria Street, Kitchener — closed until end of 2016, to build an LRT and road underpass at railway tracks.
•Park Street, between Agnes and Cherry streets, Kitchener — closed until mid-September, for track work at the adjacent GO train yard to give space for trains as King underpass work starts immediately to the east.