09-04-2015, 07:35 AM
(09-02-2015, 10:16 AM)timio Wrote: Interesting to see that only one set of tracks was laid across Seagram during the closure.
I have a hunch that this has to do with the close proximity of the Seagram (Waterloo Park) station to the road:
Remember that stations along the spur will have Gauntlet Tracks, and perhaps the crews don't have the equipment (switch components, wide ties, non-standard road decking plates) on-site yet to install these. Note that no switches up at the OMSF have been installed yet either.