11-05-2015, 08:20 PM
I think the Borden pour was just for sidewalks. Drove by just now and there was no additional track embedding done, but the sidewalks were freshly poured.
Curbs are ready to be poured tomorrow along Charles from Borden to Stirling (WB)
There's only one section of embedded track left at Benton before they can pave it to reopen next week.
They've started digging up more of Charles in front of the parking garage.
Ontario's closure was extended by over a week, for some reason.
King St (SB, KCI to Wellington) was paved today! Looks great.
Track is now in along Caroline across FDB. Just needs to be embedded.
Curbs are ready to be poured tomorrow along Charles from Borden to Stirling (WB)
There's only one section of embedded track left at Benton before they can pave it to reopen next week.
They've started digging up more of Charles in front of the parking garage.
Ontario's closure was extended by over a week, for some reason.
King St (SB, KCI to Wellington) was paved today! Looks great.
Track is now in along Caroline across FDB. Just needs to be embedded.