12-02-2015, 07:49 PM
Today's update:
Northbound portion of King have been paved between Louisa and KCI. Major work going on at Wellington, so nothing there yet.
Curbs are in from Water to Ontario. The third curb (dividing the LRT from the auto traffic) is only running from Water to under Manulife right now. It's actually possible at this rate that this portion could be paved by the end of the week!
Curbs now completely in from Benton to Cedar. Southbound curbs are in from Cedar to Madison.
Catpoles have been poured from Madison to Stirling. Some trenching was going on there tonight, look alike they just need to finish that and the retaining wall, and the curbs can go in here too.
Borden has had its grade raised significantly. Its intersection at Charles is scheduled to close next Monday, for 2 weeks. Not sure what for. Was underground work done in the intersection already?
Northbound portion of King have been paved between Louisa and KCI. Major work going on at Wellington, so nothing there yet.
Curbs are in from Water to Ontario. The third curb (dividing the LRT from the auto traffic) is only running from Water to under Manulife right now. It's actually possible at this rate that this portion could be paved by the end of the week!
Curbs now completely in from Benton to Cedar. Southbound curbs are in from Cedar to Madison.
Catpoles have been poured from Madison to Stirling. Some trenching was going on there tonight, look alike they just need to finish that and the retaining wall, and the curbs can go in here too.
Borden has had its grade raised significantly. Its intersection at Charles is scheduled to close next Monday, for 2 weeks. Not sure what for. Was underground work done in the intersection already?