RE: Drewlo Downtown project | 22 & 18 fl | U/C - tomh009 - 08-22-2019

    Work continuing at a solid clip ...


RE: Drewlo Downtown project | 22 & 18 fl | U/C - tomh009 - 08-30-2019

Early morning this time.

   


RE: Drewlo Downtown project | 22 & 18 fl | U/C - panamaniac - 08-30-2019

What would the function be of the line of "portholes" in the outer wall on the King St side?


RE: Drewlo Downtown project | 22 & 18 fl | U/C - ZEBuilder - 08-30-2019

(08-30-2019, 10:04 AM)panamaniac Wrote: What would the function be of the line of "portholes" in the outer wall on the King St side?
could that have something to do with shoring?


RE: Drewlo Downtown project | 22 & 18 fl | U/C - Coke6pk - 08-30-2019

Air ventilation for the secret tunnels to DTK and the Demogorgon?


RE: Drewlo Downtown project | 22 & 18 fl | U/C - jeffster - 08-30-2019

(08-30-2019, 10:20 AM)Coke6pk Wrote: Air ventilation for the secret tunnels to DTK and the Demogorgon?

I knew it! I knew there was a connection!


RE: Drewlo Downtown project | 22 & 18 fl | U/C - mastermind - 09-03-2019

(08-30-2019, 10:18 AM)EBuilder Wrote:
(08-30-2019, 10:04 AM)panamaniac Wrote: What would the function be of the line of "portholes" in the outer wall on the King St side?
could that have something to do with shoring?
Hi panamaniac.  ZEBuilder is correct, it is for the shoring.  In previous photos you can see the tiebacks at each steel pile.  Also below is a snapshot of a drawing for this sort of thing.  It is a common method to support the shoring (and also in this project's case a method to puncture water mains lol).

It is unusual to see them box out each tieback like this, most often the concrete just covers up whatever steel is protruding from the shoring.  Perhaps it was too big and it interfered too much with the wall structure.  Regardless, those "portholes" will be patched in with concrete after the underground is complete and they can cut the tieback steel out of the way.


RE: Drewlo Downtown project | 22 & 18 fl | U/C - panamaniac - 09-03-2019

(09-03-2019, 01:08 PM)mastermind Wrote:
(08-30-2019, 10:18 AM)EBuilder Wrote: could that have something to do with shoring?
Hi panamaniac.  ZEBuilder is correct, it is for the shoring.  In previous photos you can see the tiebacks at each steel pile.  Also below is a snapshot of a drawing for this sort of thing.  It is a common method to support the shoring (and also in this project's case a method to puncture water mains lol).

It is unusual to see them box out each tieback like this, most often the concrete just covers up whatever steel is protruding from the shoring.  Perhaps it was too big and it interfered too much with the wall structure.  Regardless, those "portholes" will be patched in with concrete after the underground is complete and they can cut the tieback steel out of the way.
Thanks for the info!


RE: Drewlo Downtown project | 22 & 18 fl | U/C - white_brian - 09-03-2019

Looks like they are working on the base of the Cameron side tower


RE: Drewlo Downtown project | 22 & 18 fl | U/C - jeffster - 09-03-2019

Speaking of Drewlo, Allan Drewlo had an interesting read over on LinkedIn. He was talking about SIS, in London, and his desire to keep it away from their buildings. Good read if you have an account with that odd social media provider.


RE: Drewlo Downtown project | 22 & 18 fl | U/C - ZEBuilder - 09-04-2019

They were bringing in another mobile crane this afternoon or they were swapping cranes. They also poured a working floor for them to build the rebar foundation on so they aren't tripping over dirt, On the corner of Charles and Cameron.


RE: Drewlo Downtown project | 22 & 18 fl | U/C - white_brian - 09-05-2019

Two cranes running at the same time


RE: Drewlo Downtown project | 22 & 18 fl | U/C - Square - 09-06-2019

(09-05-2019, 06:00 PM)white_brian Wrote: Two cranes running at the same time
Mobile cranes or tower cranes?


RE: Drewlo Downtown project | 22 & 18 fl | U/C - ZEBuilder - 09-06-2019

(09-06-2019, 03:54 AM)Square Wrote:
(09-05-2019, 06:00 PM)white_brian Wrote: Two cranes running at the same time
Mobile cranes or tower cranes?
Mobile cranes


RE: Drewlo Downtown project | 22 & 18 fl | U/C - Spokes - 09-06-2019

You've got to think a tower crane gets put up soon right?