595 Strasburg Rd | 9 fl | U/C - Printable Version +- Waterloo Region Connected (https://www.waterlooregionconnected.com) +-- Forum: Land Development and Real Estate (https://www.waterlooregionconnected.com/forumdisplay.php?fid=4) +--- Forum: Suburbs (https://www.waterlooregionconnected.com/forumdisplay.php?fid=7) +--- Thread: 595 Strasburg Rd | 9 fl | U/C (/showthread.php?tid=1624) |
595 Strasburg Rd | 9 fl | U/C - ZEBuilder - 10-23-2021 595 Strasburg Road
595 Strasburg Road, Kitchener
Developer: Unknown
A 9 floor residential building is under construction at 595 Strasburg road. The building will be 9 floors and will have 2 floors of underground parking which will be shared with the neighbouring 8 floor building at 593 Strasburg road as the building is being constructed on what was the parking lot for the building. The building will have 107 rental units over the 9 floors. There are currently no renders for the property.
RE: 595 Strasburg Rd | 9 fl | U/C - ZEBuilder - 10-23-2021 The site is currently being excavated and its about 1.5 floors down as of today. Rebar has been delivered to the site as well but progress on the site has been fairly slow over the last few months. There are a few posts in the General Suburban updates thread about this project including some pictures. The site as of today: RE: 595 Strasburg Rd | 9 fl | U/C - KevinL - 10-24-2021 Notably this is the same parcel of land as its neighbour 593 Strasburg, and until this spring was that building's parking lot. The new building is expected to have sufficient garage parking for both. The residents have been parking on nearby roadsides since construction started. I haven't heard what the plan is for the upcoming winter. RE: 595 Strasburg Rd | 9 fl | U/C - jeffster - 10-24-2021 (10-24-2021, 07:15 PM)KevinL Wrote: Notably this is the same parcel of land as its neighbour 593 Strasburg, and until this spring was that building's parking lot. The new building is expected to have sufficient garage parking for both. That would be a pain in the ass, especially when you're moving groceries. I'd imagine the city will give up exemptions during the construction period, though during a declared snow emergency, they'll likely have to park over at Zehrs. Unless most of the tenants have been renovicted, in which case, no issues. RE: 595 Strasburg Rd | 9 fl | U/C - KevinL - 04-22-2022 A slab pour was recently completed, and they've started putting in precast walls and other components; this differs from its neighbour where the work is being cast in place. ![]()
RE: 595 Strasburg Rd | 9 fl | U/C - KevinL - 06-28-2022 The first above-ground storey is being assembled. There's a faux-brick texture on the exterior of the precast.
RE: 595 Strasburg Rd | 9 fl | U/C - KevinL - 08-19-2022 The brick look is just the first three storeys, it's plain above that.
RE: 595 Strasburg Rd | 9 fl | U/C - KevinL - 10-12-2022 They've topped out at 9 storeys. ![]()
RE: 595 Strasburg Rd | 9 fl | U/C - ac3r - 10-13-2022 It looks like a Khrushchoba. RE: 595 Strasburg Rd | 9 fl | U/C - Lens - 10-13-2022 God that's bad. It'll make the building next door look good! RE: 595 Strasburg Rd | 9 fl | U/C - ijmorlan - 10-13-2022 It’ll be fine once they apply the Insulbrick. RE: 595 Strasburg Rd | 9 fl | U/C - ZEBuilder - 11-18-2022 They now have signs up saying occupancy in February 2023. It seems like a tight timeline since they still have the parking garage between the two buildings to complete. The interior seems to be progressing quickly though so they might have everyone park on the street like the current building if the garage isn't complete. RE: 595 Strasburg Rd | 9 fl | U/C - Ellensparky - 03-29-2023 What’s the status on this? Is it occupied yet? RE: 595 Strasburg Rd | 9 fl | U/C - ZEBuilder - 03-29-2023 (03-29-2023, 10:43 PM)Ellensparky Wrote: What’s the status on this? Is it occupied yet? It is definitely not occupied yet. They are still finishing the underground parking garage where the crane was sitting when they were building the tower, they just finished excavating that area 2 weeks ago. The interior of the building looks to be onto detailed finishing like flooring and appliances on the lower floors, and drywall is almost complete on the last few floors of the building. Early summer seems to be a reasonable time for occupancy of lower floors. RE: 595 Strasburg Rd | 9 fl | U/C - ZEBuilder - 04-06-2023 Here's a updated picture, the working floor is complete for the remainder of the parking garage so structural work should be starting soon. |