03-14-2024, 09:59 PM
(03-14-2024, 09:43 PM)nms Wrote: It wasn't clear to me from the article: if the City approved the proposal as requested, on what grounds did the developer go to the OLT?
It was appealed to the OLT since the city didn't respect section 22(7) of the planning act which requires the city to have a decision on the OPA within 120 days. What was appealed was never approved, neither is the current iteration which can only be approved through a settlement agreement, not the standard OPA/ZBA approval process.