04-10-2024, 03:52 PM
That last photo Jan 22nd was the 4th floor slab. Now 2.5 months later they are working on the 9th floor slab. That's a floor per two weeks. There's 10,11,12, and roof left. The roof always seems to take a bit longer so call it two floors, so maybe 2.5 more months and the structure could be finished.