04-10-2024, 08:14 PM
(04-10-2024, 07:27 PM)tomh009 Wrote: This is construction fencing, not just for demolition, so I have to believe that they will start this as soon as demolition is done.
They don't even have demolition permits yet, something was amiss in their first applications as all of the demolition permits have recently been resubmitted, the exception is the Onward factory which is still on it's original application.
The only other permit they have applied for is a foundation/site servicing permit, generally they'll still need to get a shoring permit before they can proceed with any underground construction.