(03-24-2026, 01:43 PM)Momo26 Wrote: What was thrown out there for initial occupancy for this project?
I doubt that there is any firm date published. The excavation for the current buildings under construction (A, B and C) didn't start until 2024, whereas the preliminary construction schedule had them under construction from 2020-2023 (see post #459 in the thread).