10-23-2015, 02:32 PM
Latest Ion update is available online.
Some highlights:
Seagram is closing on Monday for 2 weeks to install tracks.
Track is being installed along Caroline - at Alexandra starting Oct 26
King street will be prepped for paving from Green to Wellington starting Oct 29
Charles from Water to Queen is almost ready for paving; only a few watermain connections to be done.
Borden will be fully reconstructed by mid-November
Some highlights:
Seagram is closing on Monday for 2 weeks to install tracks.
Track is being installed along Caroline - at Alexandra starting Oct 26
King street will be prepped for paving from Green to Wellington starting Oct 29
Charles from Water to Queen is almost ready for paving; only a few watermain connections to be done.
Borden will be fully reconstructed by mid-November