07-28-2016, 05:57 AM
Just guessing: but maybe the Region is going to wait until GrandLinq is done, then take care of adding a crossing on their own?
Asking them to rework the design and integrate a crossing at this point is a scope change and could open up a can of worms - giving GrandLinq and opportunity to delay their "Substantial Completion" date, increase their cost, etc - might be like the Waterloo Park fence thing (easier for the Region to just do it on their own afterward - obviously with integration to the VMS and everything since it'd need to have signal arms due to train speeds here).
Asking them to rework the design and integrate a crossing at this point is a scope change and could open up a can of worms - giving GrandLinq and opportunity to delay their "Substantial Completion" date, increase their cost, etc - might be like the Waterloo Park fence thing (easier for the Region to just do it on their own afterward - obviously with integration to the VMS and everything since it'd need to have signal arms due to train speeds here).