Correct, it's Kitchener Hydro work. Closed about a month ago:
1/3 - Saturday, March 4, 2017
The track on the Southbound alignment seems to be connected under the long hoarding tent; rails on the Northbound alignment are getting ready to go.
The contact wire for the run Charles/Borden Southbound has been strung.
Platform speakers at Northfield. The platforms for the Waterloo Spur stations need to be completed before LRV's can use the test track, so there's currently a big push to get them wrapped up.
Cameras, platform speakers...
Does anyone have any ideas what these could be for?
@RadagastWiz @Canardiain @CTVKitchener @WR_Record @570NEWS @570traffic Yes. The work will support ION. https://t.co/O5hu1Cl0FA
— KWHydro (@KWHydro) February 11, 2017
1/3 - Saturday, March 4, 2017
The track on the Southbound alignment seems to be connected under the long hoarding tent; rails on the Northbound alignment are getting ready to go.
The contact wire for the run Charles/Borden Southbound has been strung.
Platform speakers at Northfield. The platforms for the Waterloo Spur stations need to be completed before LRV's can use the test track, so there's currently a big push to get them wrapped up.
Cameras, platform speakers...
Does anyone have any ideas what these could be for?