Final paving will be happening downtown starting this Sunday for about 2 weeks:
Starting as early as June 18, crews will begin to complete final asphalt paving in Downtown Kitchener. The following closures are required for this work:
Victoria, from Waterloo to Charles, will close nightly on or about June 18 at (7 p.m. to 7a.m.) for approximately two nights
Starting as early as June 18, crews will begin to complete final asphalt paving in Downtown Kitchener. The following closures are required for this work:
Victoria, from Waterloo to Charles, will close nightly on or about June 18 at (7 p.m. to 7a.m.) for approximately two nights
- Intersections impacted: Victoria/Charles and Victoria/King
- Intersection impacted: King/Francis
- Intersection impacted: Francis/Duke
- Intersections impacted: Charles/ Francis; Charles/Water; Charles/ Gaukel,
- In preparation for this paving the following intersections will need to close for one day:
- Charles/Francis will close on or about June 20
- Charles/Gaukel will close on or about June 20
- Charles/Water will close on or about June 21
- Intersections impacted: Charles/Ontario; Charles/Queen
- In preparation for this paving the following intersections will need to close for one day:
- Charles/Queen will close on or about June 20
- Charles/Ontario will close on or about June 21
- Charles/Benton will close on or about June 22