(04-13-2018, 07:50 PM)Pheidippides Wrote: Thinking about the new proposed schedule, December 2018 seems unattainable.
Even if they ship one every two weeks, which they haven't done yet, the 14th vehicle would arrive in mid-August. Adding 6 months puts it at February 2019.
Even if they ship one every per week the 14th vehicle would arrive in late-June. Adding 6 months puts it at late December 2018; and that is if everything goes absolutely perfectly, which is highly unlikely given.
Do we know if 501 will be the last to be (re) delivered? It will be unfortunate if that is the hold up when it sat here for nearly a year.
But why should we need to run that very last train for eight (or six) months? Can someone explain this to me?