05-09-2018, 09:17 PM
(05-09-2018, 08:32 PM)Canard Wrote: Finch just had it's tender put out - 2.5 bn for 11 km of LRT. 4.8x the cost of ion for what they're getting.
I have always said that the team here did an excellent job of absolutely maximizing the size of the system for as little money as possible.
Are you sure you’re not including operations and maintenance in that number? If that is the contract value, I think it compares more closely to our $1.9G Grandlinq contract than to our $880M capital expenditure.
Still, it does seem we’re getting pretty good value.