Or two, or ten, or 9 years - just on average from my observations of following many projects, three is about the bare minimum, from first pull-through, to service start. Our system is more complex, so I imagine it will be closer to nine than three.
Posts: 625
Threads: 4
Joined: Jul 2016
Reputation:
22
And also, what's the latest word on the initial tests on the track with the first vehicle? October?
Posts: 1,709
Threads: 2
Joined: Aug 2014
Reputation:
35
Canard, you think it will be three more years, 2020, before service starts?
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
08-31-2017, 07:39 PM
(This post was last modified: 08-31-2017, 07:40 PM by Canard.)
Oh, haha! I meant months. Jeez.  Well, maybe it will be!
Yes, all indications I've heard is that in October, we'll see 502 out in the tracks, shortly after it arrives.
Posts: 487
Threads: 0
Joined: Oct 2014
Reputation:
22
I don't even think we can start making estimates on when it'll go live until the 2nd train gets here and starts being tested. Right now we essentially have nothing and no reason to trust the estimates from Bombardier.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
I'm amazed it went to Ottawa and back without a peep. I suspect Tiger meant one of the Metrolinx pilots.
Posts: 1,095
Threads: 2
Joined: Aug 2014
Reputation:
33
09-01-2017, 07:41 AM
(This post was last modified: 09-01-2017, 07:44 AM by timio.)
(09-01-2017, 06:32 AM)Canard Wrote: I'm amazed it went to Ottawa and back without a peep. I suspect Tiger meant one of the Metrolinx pilots.
That was my guess as well, seeing as BBD said it was Metrolinx LRV 1 that went to Ottawa.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
Posts: 4,604
Threads: 16
Joined: Aug 2014
Reputation:
150
Quote:"One of the things we've never gotten an answer for is Bombardier is already producing this vehicle in Europe. So why can't Bombardier North America produce it?" Galloway said.
Truly a question for the ages.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
It's not. FLEXITY Freedom is a variant of the FLEXITY 2 from Europe. It's a brand new product - we're the launch customer. It only looks the same on the outside. The bones are totally different.
Posts: 2,893
Threads: 3
Joined: Mar 2015
Reputation:
99
(09-01-2017, 09:09 PM)Canard Wrote: Software: The Latest Snafu - The Record
Yep, just read that, was going to post it but saw you beat me to it.
Hate to be negative, at this rate though, 2018 seems optimistic. It shall be a rough year for politicians if this isn't up and running before October 2018....
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
09-02-2017, 08:15 AM
(This post was last modified: 09-02-2017, 08:20 AM by Canard.)
For all we know, it could be super-strict certification-type stuff with Transport Canada that is causing Bombardier all the headaches. It's conceivable that there's a totally different protocol here for the programming, since it's running as a "railway" for part of the line - something they didn't have to do for the FLEXITY Outlook LRV's for Toronto. You'd think Bombardier would try to defend themselves by pointing out something like that, but maybe they're bound not to by some kind of legal agreement.
Posts: 281
Threads: 0
Joined: Jul 2016
Reputation:
31
That seems like a pretty big reach. The most likely reason seems that they're just behind - whether the schedule was too aggressive or they hit unanticipated problems. The reason they're not "defending" themselves is that its just their fault.
Posts: 6,905
Threads: 32
Joined: Oct 2014
Reputation:
224
I'm just saying - if LRV No. 1 showed up here without software, and 6 months later it still doesn't have working software... there is probably a good reason beyond what we are privy to.
(I personally have always thought 501 is probably a lemon, and would need to go to Millhaven to be rebuilt right - and now it sounds like that's exactly what is going to happen!)
Posts: 281
Threads: 0
Joined: Jul 2016
Reputation:
31
09-02-2017, 02:34 PM
(This post was last modified: 09-02-2017, 02:35 PM by SammyOES2.)
(09-02-2017, 01:55 PM)Canard Wrote: I'm just saying - if LRV No. 1 showed up here without software, and 6 months later it still doesn't have working software... there is probably a good reason beyond what we are privy to.
I guess, but my point is just that thinking its likely an external factor like Transport Canada vs an internal factor at Bombardier is giving them the benefit of the doubt, which they definitely haven't earned. It's not like writing software is a super reliable and predictable thing and any delay is likely to be caused by something else.
So, yeah, I take your point that its possible its not Bombardier's fault. I just think thats really unlikely. Not even accounting for the fact that if it IS an external factor they probably still should have been able to plan for it ahead of time.
|