(06-17-2015, 06:24 PM)DHLawrence Wrote: What is the schedule for raising the line? Will they be able to do it without disrupting VIA service?
It's starting now, that's why they've closed King from Victoria to Wellington and now Waterloo St. It will be closed for 18 months for construction. Because it's CN's north mainline it will be done without disrupting service. I believe the plan is to construct a temporary track at the current grade, and then a new track at the new grade, then they can do a weekend switchover from temporary track to new track.