Zehr posted a picture of the Glove Box tower crane coming down on their Instagram story today. Based upon the picture they have it looks as if they're using the Garment Street tower crane to take down the Glove Box tower crane instead of using a mobile crane which is what would typically be used.
Posts: 4,913
Threads: 155
Joined: Aug 2014
Reputation:
119
Curious if Zehr/Momentum will try to snatch up more property in this area after the Garment/Glove/100 project has gone so well
Posts: 1,521
Threads: 13
Joined: Aug 2014
Reputation:
123
Zehr/Momentum aren't doing joint projects anymore.
For Momentum they're doing Q Condos next, and then the Atrium/Angies property in uptown (that's owned by them, not Zehr Group as I initially said). Without Zehr I think that'll keep them busy for the next couple years, they don't have the capacity for much more.
I think Zehr might be considering it though. I don't know what they've got in the pipeline beyond their Belmont project.
Posts: 6
Threads: 0
Joined: Mar 2021
Reputation:
0
Can someone confirm whether tower 3 officially got delayed until Jan/Feb 2022? Heard there was an email that got sent out already.
Posts: 3,859
Threads: 63
Joined: Jul 2015
Reputation:
201
The last tower has topped out and they are currently taking down the tower crane today.
Posts: 27
Threads: 0
Joined: Jan 2019
Reputation:
1
Looks like delayed closings once again for this last tower due to a flood.
"On March 26, 2022, a pipe burst on the 18th floor of the Garment Street condominium development, allowing water to flood throughout the building over the next 36 hours. The flooding has resulted in significant damage to various components of the building. The clean-up process is well underway and the damage to the building is being assessed by 114-120 Victoria Street South Inc., and the construction team."