(07-18-2017, 03:34 PM)GtwoK Wrote: I noticed that according to the King St reconstruction plan, Phase A of the construction (Bridgeport to Erb) is supposed to last 14 weeks, starting from April 17th. That brings completion of Phase A to the end of next week.... that CAN't be right. From what I've seen, they've barely even started on underground work from Bridgeport to Princess, and JUST started underground work From Princess to Dupont. How is all of that, PLUS electrical, PLUS installation of the underground tree-box things, PLUS curbs, PLUS lighting, PLUS asphalt supposed to be done by next week? How far behind are they on this?
They are quite behind, as you surmise, they initially had issues with getting the water supply approved, which is apparently a time consuming process. They have apparently brought in more crews however. I am not sure what the current expected completion date will be though.