09-19-2018, 06:33 PM
(09-19-2018, 06:08 PM)Pheidippides Wrote: The document says installation is half-way done on 502/504/504 after starting on July 16. Installation is "expected to be complete in late September/early October."
July 16 to October 1 is 77 days (54 work days).
54 workdays from October 1 is December 18.
That's cutting it pretty close (and that's not including at testing of the newly installed equipment).
Even if they half the time for the next 5 Waterloo installations, which seems unlikely given that there would be 5 not the current 3 they are working on, that would be 27 days or November 8 - still not a lot of wiggle room.
Why October? The document was published today. The 51% progress update is surely from some time earlier. If we assume it's from last Friday, for example, it's 43 work days. Add another 43 days to last Friday and we get 16 November 2018.