(12-18-2018, 04:27 PM)Momo26 Wrote: So tell me if there is anything to this: reason for delay is not so much inadquate or late shipments of trains, but that they have to rip up part of King street and re-do the road/LRT as legally, there has to be space for an emergency vehicle to be able to pass (and at this point, with only one lane going each way and LRT taking the rest, there is none)?
In my opinion there's nothing to that.
They can't rip up and re-do King St between now and spring, and its perfectly sensible that they couldn't launch in December when all vehicles weren't complete with FIE installed until the very end of it, as that left no time for the required integration testing and burn-in.
...K