(04-01-2019, 12:28 PM)nms Wrote: What's the typical ratio of "bid takers" vs "tenderers" in a case like this? It would appear that five companies took the bid documents for the UW station, but only two submitted bids. The Region also rejected going ahead with the King-Victoria development. Was there a similarly small pool of groups that bid on Ion? (I seem to recall there were three... how many others showed interest?).
There isn't any kind of standard. For this project there was a pre-qualification stage. At that point it looked like about 12 contractors took the package. Only 3 submitted for the PQ. And then only 2 submitted for the bid itself. One of the prequalified bidders didn't take the bid package, the other 3 are construction associations who grab every bid for their members.
On a typical project a number of bid takers could also be subcontractors who register to make sure they get all of the addenda as the GC's may not pass these along quickly enough.