06-21-2021, 08:39 PM
(06-09-2021, 10:57 AM)ac3r Wrote:(06-08-2021, 09:29 PM)tomh009 Wrote: The planning department has not uploaded it. Apparently it's available on request.
They don't seem to reply anyway. About two weeks ago I requested the documents for this project and got no response.
The city sent me the document. The file is too large to let me post here but if you want a copy you can PM me and I’ll email it over
Notably :
Height of Tower B = 92m
Tower C = 100m
Tower D = 120m
Tower E - unspecified height, but looks to be hotel and not residential on top of the office ( I’m not sure if this was originally the plan) 1 floor retail. 9 floors commercial and 24 floors hotel = 34 floors and not 44 ( although I’m not good at reading these things)