07-11-2015, 01:27 PM
(07-11-2015, 11:41 AM)Canard Wrote: Talked to some GrandLinq folks this morning on site. Here's the scoop:
-12 boxes currently installed for SB track
-18 more next weekend for NB track
-Bridge comes out next Friday
-CN is giving them a 130+ hr window that they HAVE to hit, so next weekend is a big weekend
-tracks reinstalled by Wednesday
-In about a month, track installation will continue from the OMSF, heading south
-A good chunk of final spur line track will be done this year
Thank you. Did you ask them if they will have a new bridge here like the one on Hayward or just the culvert?