In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 3 Vote(s) - 1.33 Average
  • 1
  • 2
  • 3
  • 4
  • 5
Weber Yards (1333 Weber St E) (nee Elevate Condos) | 15, 15, 12 & 12 fl | U/C
So they thought it would be an easy investment so they jumped in and bought a unit without doing ANY research into the developer (there were a lot of red flags with the first one, see below), regret it now that things are tanking and expect the money back. Haha.

Don't. Build. Pre-construction. Units!

[Image: YvE46WN.jpeg]
Reply


And back in the news...again!

https://www.ctvnews.ca/kitchener/article...rmination/

Lmao what's with the pic ^
Reply
Good luck seeing the rest being built in the next 20 years, unless they make them rentals.
Reply
(10-02-2025, 09:18 PM)Momo26 Wrote: And back in the news...again!

https://www.ctvnews.ca/kitchener/article...rmination/

Lmao what's with the pic ^

That was the developer who initially tried to do this project, then let it fall apart. Not a guy I'd trust in a sword fight or business meeting.
Reply
https://www.ctvnews.ca/kitchener/article...ner-tower/
Reply
This building looks abandoned, has anyone moved in?
Reply
(01-26-2026, 09:25 PM)ibuildstuff Wrote: This building looks abandoned, has anyone moved in?

Yes occupancy is permitted in building A.

Permits are issued for building B and C but construction has not commenced on anything beyond the underground.
Reply


Was driving past this recently and saw a crane being erected on site. Is this development back up and running?
Reply
(09-07-2026, 10:21 AM)Archetype Wrote: Was driving past this recently and saw a crane being erected on site. Is this development back up and running?

To some degree, yes.

Elm has spent the last few years working through some of the more nuanced technical portions of the project including financing to start on the next towers. They had permits for Tower B and C issued in 2025 before the water issue as such they can go ahead unlike other projects.
Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 1 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links