In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 16 Vote(s) - 4 Average
  • 1
  • 2
  • 3
  • 4
  • 5
ION - Waterloo Region's Light Rail Transit
The Northfield platform is being poured today.
Reply


(05-02-2016, 02:22 PM)Square Wrote: What does this quote from the ION Update mean?  "•Work to install the Victoria Park  LRT stop will begin in May"   I thought the stop is already poured, or are they going to start the anchor wall and other parts?

I imagine things like the approach ramps at either end, the platform surface, etc; though it may be actual staton fittings like the anchor wall, shelters, etc as well.
Reply
Would be surprising, but then again, it WAS the first station to be poured. It's also possible it was a typo. Those Ion updaters do a lot of copy-pasting, sometimes have incorrect remnants from other updates in them.
Reply
(05-02-2016, 04:11 PM)GtwoK Wrote: Would be surprising, but then again, it WAS the first station to be poured. It's also possible it was a typo. Those Ion updaters do a lot of copy-pasting, sometimes have incorrect remnants from other updates in them.

Thank you for the replies.  Ya, I was thinking maybe they meant Queen St stop?
Reply
(04-20-2016, 10:16 PM)timio Wrote: So, for the fun of it, a list of intersections / streets where work is still to begin:

Victoria: King to Charles
Frederick: Duke to Charles
Ottawa: Courtland to Mill
Erb/Caroline (closes May 16)

Did I miss anything?

Down to Victoria, Frederick, and the western part of Ottawa (Mill to Courtland)

Any bets on when they'll start the final two downtown stretches? After Water and Queen intersections are open? According to rideion.ca, they should be open in the next month.

*Removed sections underway
Reply
King St is now torn up between Francis and Victoria, so that one can come off the list.
Reply
*fixed
Reply


   
Tampy McTampface was out again in full force this afternoon.

   
His buddy, Mr. Blowystones, was also having a bit of a romp.

   
Like a snowblower for ballast.

   
Ties and trackwork.
Reply
   
Track switch on site in front of Perimeter.

   
Huuuuuge double-wide concrete ties!

   
Switch nameplate, more here.

   

   
Frog detail.
Reply
Curb-laying guides are in between Victoria and Francis, curbs will probably be going in there tomorrow or Wednesday.

Traffic poles are also up at Charles / Ontario.

Charles / Queen has been refilled in and tampered. They'll need to get a move on, with less than 2 weeks to do curbs, lay track, embed it, and pave it here.

Embedded track is almost done through the Eby intersection. It seems like Eby will carry through traffic once this is all done? That must have changed. In the original plan it was RIRO at Charles. Anyone know what's up?
Reply
Certainly lots going on along Charles! Here's the ever-farther pour progress towards Eby.

[Image: Kf2MFIK.jpg]

A quick peek at Benton/Frederick around King. Utility work is finished for now on Benton and is shifting more and more Duke-ward.
[Image: DYKDwvQ.jpg]

The Queen intersection is looking relatively polished.
[Image: cSXYVJL.jpg]

And, in front of the bus terminal, it looks like they're preparing to restore the sidewalk.
[Image: ptUJtIu.jpg]
Reply
(05-02-2016, 09:05 PM)GtwoK Wrote: Embedded track is almost done through the Eby intersection. It seems like Eby will carry through traffic once this is all done? That must have changed. In the original plan it was RIRO at Charles. Anyone know what's up?

I don't think the plan has changed - but I think they may open it to traffic temporarily, while they do the full pour on the Cedar intersection.
Reply
That was my thought, too.
Reply


(05-02-2016, 09:27 PM)KevinL Wrote:
(05-02-2016, 09:05 PM)GtwoK Wrote: Embedded track is almost done through the Eby intersection. It seems like Eby will carry through traffic once this is all done? That must have changed. In the original plan it was RIRO at Charles. Anyone know what's up?

I don't think the plan has changed - but I think they may open it to traffic temporarily, while they do the full pour on the Cedar intersection.

That would make sense. I do question the fact that the curbs around that intersection have nicely poured "endcaps", so to speak, rather than rough ends like they've used at other temporary crossings though.
Reply
3 fresh curbs Francis to Victoria on Charles:
   
   
Everyone move to the back of the bus and we all get home faster.
Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 6 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links