01-08-2022, 08:51 PM
(01-08-2022, 08:35 PM)ZEBuilder Wrote:(01-08-2022, 07:23 PM)CP42 Wrote: It seems odd that there is no occupancy yet, even on the lower floors. Didn’t Charlie West top out at roughly the same time, yet it is almost fully occupied?
Charlie West topped out in the middle of January with the first occupancy occuring in August so a 7 month difference, Duke tower topped off in late June. If it's following the same 7 month schedule as Charlie West it should get occupancy later this month.
From there most recent YouTube video which was posted 2 weeks ago they said that the 15th floor has kitchen installs occuring so that furthers the idea that occupancy isn't far off.
Makes sense. The first tower of Station Park topped out in December and they have given an estimated occupancy of July - following a 7 month timeline as well.