In order to take advantage of all the great features that Waterloo Region Connected has to offer, including participating in the lively discussions below, you're going to have to register. The good news is that it'll take less than a minute and you can get started enjoying Waterloo Region's best online community right away.
or Create an Account




Thread Rating:
  • 0 Vote(s) - 0 Average
  • 1
  • 2
  • 3
  • 4
  • 5
King Street underpass at the transit hub
(02-08-2016, 07:03 PM)kps Wrote:
(02-08-2016, 01:53 PM)KevinL Wrote: […] the railway (CN) dragged their feet on approvals, etc.
Why CN? Metrolinx bought the section in 2014.

CN is still the deciding authority for railway clearances etc since their equipment, or that of another company handling their freight traffic, will operate through the space.  The same thing happened with the Waterloo Spur where CN was one of the final approval steps for all trackwork.
Reply


Picture from this morning. Not only is the covering over most of the North half of the larger snodome (as previously reported), they've begun excavating the surface down to the level to regrade the road (and LRT track!).
   
Reply
Looking through the domes, from Park Street.

[Image: OpNLok1.png]
Reply
Glorious puddle wallpaper.

   

Watching paint concrete dry.

   
Reply
Will this dome ever get closed?
Reply
Yes, but not until they need to. Since it will make it more difficult to move equipment in and out once it is closed off, that won't happen until the pours that require it are ready to happen. We're close.

On the weekend, the smaller dome had cross bracing up in preparation for tarping.
Reply
The smaller dome is now closed off on the west side.
Reply


Thank you.
Reply
You're welcome! Smile

The critical pour is the deck on top, which is a staggering two metres thick. The temperature must be at 10C for at least a week for the concrete to properly set.
Reply
Why is this deck so much different than the Weber St rail overpass? That one is just steel, isn't it?
Reply
I definitely overheard a conversation where a nearby resident complained about the dome, wondering why it was needed when the Weber underpass didn't require one.
Reply
The King St deck is concrete where Weber St is two single track steel sections
Reply
Here is the "dome view" as seen from the Margaret St bridge.


Attached Files Image(s)
   
Reply


Wow not a lot of room from that angle, gonna be a tight squeeze to put in another line?
Reply
I find people that complain* about things like the dome kind of funny.

In general (although certainly not always) the people in charge of these types of decisions know what they're doing way better than a random joe. They probably didn't decide to just throw away one or two million dollars on a whim.

* Complaining is different than questioning. I like finding out *why* these things are needed.
Reply
« Next Oldest | Next Newest »



Forum Jump:


Users browsing this thread: 2 Guest(s)

About Waterloo Region Connected

Launched in August 2014, Waterloo Region Connected is an online community that brings together all the things that make Waterloo Region great. Waterloo Region Connected provides user-driven content fueled by a lively discussion forum covering topics like urban development, transportation projects, heritage issues, businesses and other issues of interest to those in Kitchener, Waterloo, Cambridge and the four Townships - North Dumfries, Wellesley, Wilmot, and Woolwich.

              User Links